Commissioning and handover form

Read directly in English3 min read5 tables

Commissioning and handover form

Form code: F-04 Project: …… | Date: …… | Minutes number: ……

4–1. Test information

title

amount

Employer representative

……

Contractor representative

……

Mechanical and electrical supervisor

……

Delivery operator

……

Version of base maps

……

Control program version

……

Water level during the test

……

Weather and wind conditions

……

Measuring devices and calibration validation

……

Duration of continuous performance test

……

4–2. Pre-launch review

row

item

the result

Document number or defect description

1

Matching the installed equipment with the final documents

……

……

2

Completing the sealing test and fixing the leak

……

……

3

Washing the circuit and removing the remains of the execution

……

……

4

Installation and stabilization of pumps, nozzles and lights

……

……

5

Complete suction protection and accessible vents

……

……

6

Verification of the status of valves and drain lines

……

……

7

Completion of electrical inspections and tests

……

……

8

Availability of water and purification system

……

……

9

Level control readiness and dry run protection

……

……

10

Separation of the test area from public attendance

……

……

4–3. Record performance results

equipment or circuit

parameter

Design value and tolerance

Measured value

the result

pump

Flow Rate

……

……

……

pump

Pressure or head at defined points

……

……

……

engine

Current of each phase

……

……

……

circuit

input power

……

……

……

nozzle

The height and shape of the effect

……

……

……

ring

Uniformity of appearance

……

……

……

Purification

flow rate

……

……

……

Filter

Initial pressure difference

……

……

……

the light

Voltage at the place of consumption

……

……

……

water system

Compensatory water rate in recorded conditions

……

……

……

4–4. Control tests

scenario

Expected behavior by design

Actual result

Water level drop

……

……

Disconnect control

……

……

Power cut and return

……

……

Emergency stop command

……

……

Over-adjusted wind

……

……

Pump or drive fault

……

……

Interruption of purification circulation

……

……

Departure of water quality from the approved limits, if monitored

……

……

Implementation of the schedule

……

……

Restore application backup

……

……

The error test should be performed with a controlled and verified simulation method; Deliberately creating a dangerous situation in the presence of people is not a test method.

4–5. Documents and items to be delivered

Construction drawing □ Equipment table and serial number □ Operation manual □ Electrical test report □ Mechanical commissioning report □ Maintenance schedule □ Water results □ Control backup □ Management access from secure path □ Spare parts list □ Warranty documents □ Training minutes □

4–6. Defects and delivery decision

defect

Importance

Responsible for fixing

due date

Confirmation certificate

……

Safety / functional / appearance

……

……

……

Status: ready for delivery □ conditional delivery according to the contract □ need to repeat the test □

Defects affecting safety must be fixed and confirmed before allowing public operation.

Contractor's signature: …… Supervisor's signature: …… Employer's signature: …… Operator's signature: ……

About this edition

The supplied book has been transferred into website pages, including tables, equations and footnotes. The initial translation was machine generated, with terminology corrections and sample checks; a complete human technical review has not yet been performed. The diagrams have been recreated for the web with labels in the selected language.